Dear Neighbors,
On behalf of the development team at St John’s Terminal, we are writing to you regarding upcoming construction activities occurring at 550 Washington Street between Spring St and Clarkson Streets, and between Washington and West Streets.
This is part of our ongoing effort to maintain communication between the project team and the community, and to provide construction look-ahead updates to notify our neighbors and the community about activities occurring at the site and any potential impacts they may have on the community.
Demolition continues for the North building between West Houston and Clarkson Streets, and between Washington and West Streets. The North sidewalk on West Houston Street (between Washington Street and West Street) will remain open to pedestrians for the remainder of the project. The South sidewalk on West Houston St continues be closed to the public. The off-hour work is scheduled as follows:
Weekend Fri 11/1 – Mon 11/4
The contractor will continue demolition of the 2nd floor beams & 1st floor columns south of Houston St requiring that Houston St be closed to vehicles between Washington St & West St during the following times:
- Sat 11/2 7AM – 6PM
- Sun 11/3 7AM – 4PM
*NOTE: The North sidewalk on Houston St will remain open to pedestrians at all times.
Mon 11/4 9PM – Tues 11/5 5AM
A contractor will be restriping the roadway on Washington St between Houston St & Spring St. This will be done in partial closures of the roadway. No full closure & west sidewalk on Washington St will be available to pedestrians at all times. Please see attached drawing that indicates new vehicle & bike lane traffic pattern for your reference.
Weekend Fri 11/8 – Mon 11/11
The contractor will continue demolition of the 2nd floor beams & 1st floor columns south of Houston St requiring that Houston St be closed to vehicles between Washington St & West St during the following times:
- Fri 11/8 9PM – Mon 11/11 5AM
*NOTE: The North sidewalk on Houston St will remain open to pedestrians at all times.
**At no time will Houston St AND Washington St be closed at the same time.
Week of 11/11
A mobile crane will be set-up on Washington St for the South Building Con Ed Vault Relocation during the following times. It will be set up approximately half way between Houston St & Spring St. A vehicle lane on Washington St will remain open at all times and work shall take place during normal working hours.
- Tues 11/12 6AM – Fri 11/15 6PM
If you have any questions, please do not hesitate to contact us at stjohnsterminal@kasirer.nyc. If you know of anyone else who should be receiving these emails, we encourage you to distribute our email address.
Sincerely,
The St. John’s Terminal Team